Tuesday 15 April 2014

Some progress…

We have had some progress as the MoE has now reviewed the first draft of the Master Building Plan for our local cluster of four schools, and the final QS estimate of costs has been completed.
However due to changes in the original scope of works for our cluster there have been some delays. In addition, based on Ashgrove’s latest projected roll numbers, we may now receive one less teaching space in our new building. Work has begun on a funding submission, but we are aware that this is going to be a lengthy process and building is now unlikely to start this year.
Mecca Hampton-James & Kristine Feather
Board of Trustees